Glass Replacement to Begin at the Capitol
Thursday July 8, 2021It was discovered several years ago that historic replica “chicken wire” glass installed during the renovation completed in 2009 were delaminating, or separating, internally. The effect of this is visible, especially in the rotunda, where the glass has developed round circles in areas that have delaminated. Because the glass separation may affect the integrity of the windows it is more than a simple cosmetic issue. Because of this, the Capitol Commission has been actively engaged with the original renovation contractor to arrive at a mutually beneficial agreement to share costs and complete the work.
Windows reachable by ladder both in common areas and tenant spaces will be replaced beginning the second week of June with minimal interruption for both tenants and visitors.
Reaching the skylights on the 4th floor and upper rotunda areas will require erecting scaffolding. Every level of the Capitol rotunda from the garden level to the fourth floor will have some impact from the project. The garden level will be reinforced to support a material hoist installed on the first floor and scaffolding will be installed from the second floor to the fourth. A temporary protective wall will surround the interior of the rotunda allowing the building to remain open to both tenants and visitors during the duration of the project.
Construction of the scaffolding will begin the week of July 5th with an anticipated completion date of October 15th. We will update the schedule and publish it here as the project progresses.